3 · Purchase orders and confirmation ​

Who acts: the supplier. Starts with: a purchase order (PO) arriving in the supplier's queue. Ends with: the supplier committing to all of it, part of it, or none of it.

One PO per supplier ​

Issuing a request creates one purchase order for each supplier in the plan. Each PO is its own contract, with its own lines, total, delivery or pickup, and payment method. A request for five suppliers produces five POs that move independently.

Confirming ​

The supplier checks stock and prices, then answers line by line:

Answer for a lineMeaning
In fullWill supply the quantity ordered at the price ordered
Part onlyCan supply fewer
Later dateCan supply it, but not by the date needed
SubstituteProposes an equivalent product, with its price
Can't supplyDrops the line

The supplier also confirms the delivery window or pickup point. By default the supplier has 4 hours to confirm; a late confirmation is flagged to platform staff.

Statuses you will see ​

PO issued → Awaiting confirmation → one of:
OutcomeStatusWhat happens next
Everything as orderedConfirmedOn to payment
Some lines changedPartially confirmed with Correction proposedThe buyer answers the correction before the order moves on
Nothing can be suppliedRejectedThe buyer sources those lines elsewhere

Before the supplier confirms, the buyer can still cancel the PO.

Why changes become a correction ​

The buyer ordered something specific. If the supplier can only offer something different, the buyer decides whether to take it. So every difference — quantity, price, date, substitute — is collected into one correction. The buyer accepts, counters or rejects it, and only then does the PO move on as a new version.

A high-level guide: flows, states and rules. Screen-by-screen detail lives in the product.